Qairokkum Hydropower Rehabilitation Project
About the Project
- Client:
- Open Stock Holding Company Barqi Tojik
- Location:
- Tadschikistan
- Time frame:
- 2015–ongoing
Technical Data
- Design flow: 1,062 m³/s
- Height of dam: 32 m
- Installed capacity: increase from 126 to 174 MW
- Annual production: increase from 700 to 900 GWh
- Earthfill dam, submerged power house
ILF-Services
- Management Consulting
- Project Management
- Engineering