Qairokkum Hydropower Rehabilitation Project

The Qairokkum HEPP was commissioned in 1959. Today, most of the electrical and mechanical equipment has reached the end of its lifetime and therefore a major rehabilitation is needed.
Energy & Climate ProtectionHydropower
Client:
Open Stock Holding Company Barqi Tojik
Location:
Tadschikistan
Time frame:
2015–ongoing
  • Design flow: 1,062 m³/s
  • Height of dam: 32 m
  • Installed capacity: increase from 126 to 174 MW
  • Annual production: increase from 700 to 900 GWh
  • Earthfill dam, submerged power house
  • Management Consulting
  • Project Management
  • Engineering

Proven Impact Through Real-World Projects

Explore selected projects that demonstrate our expertise in delivering complex energy and infrastructure solutions worldwide.

    Start Your Next Engineering Project with Us

    Partner with our experts to deliver complex infrastructure, energy, and environmental projects with precision and long-term impact.

    Contact Us

    Start Your Next Career Steps with Us

    Join our team and help shape sustainable solutions for the infrastructure and energy challenges of tomorrow.

    Explore Careers