Cethana Pumped Hydroelectric Energy Storage
About the Project
- Client:
- Hydro Tasmania
- Location:
- Australia
- Time frame:
- 2023–ongoing
Technical Data
- Installed capacity: 750 MW
- Upper reservoir volume: approx. 12.0 million m3
- Gross head: approx. 520 m
- Waterway length: headrace approx. 2 km and tailrace 1.3 km
- Annual generation: approx. 1570 GWh
ILF-Services
- Consulting Services
- Engineering and Design Services
- Procurement and Contracting Services
- Project Management