Nam E Moun Redesign Hydropower Project

ILF's services for the Nam E Moun project started as Owner's Engineer and assistance during the tendering process and site supervision for the construction and commissioning of the project. In addition, ILF applied RENRisk™ to optimize the project from a technical and financial perspective and identified a cost reduction potential of $20 million. During a re-design phase, several measures were formulated to secure the CoD by improving the technical design. Finally, the detailed de-sign of about 20 km of tunneling works is carried out by ILF.
Energy & Climate Protection
Client:
Confidential
Location:
Lao PDR
Time frame:
2018 - ogoing
  • Installed Capacity: 131.5 MW
  • Design Flow: 37 m3/s
  • Design Head: 396.4 m
  • Headworks:2x Gate Weirs concrete weirs (height 28 m, crest length 45 m) with lateral intake
  • Waterway: Two converging pressurized tunnels with a total length of 20 km
  • Powerhouse: 2 x vertical Pelton turbines
  • Management Consulting
  • Engineering
  • Project Management

Proven Impact Through Real-World Projects

Explore selected projects that demonstrate our expertise in delivering complex energy and infrastructure solutions worldwide.

    Start Your Next Engineering Project with Us

    Partner with our experts to deliver complex infrastructure, energy, and environmental projects with precision and long-term impact.

    Contact Us

    Start Your Next Career Steps with Us

    Join our team and help shape sustainable solutions for the infrastructure and energy challenges of tomorrow.

    Explore Careers
    Nam Emoun Redesign Hydropower Project